STATUS:

Cubicles have been built; the conference room, consultation room A; consultation room B; computer room; pantry, and lounge have been built.

Painting is on-going.

The electrical  telephone and data cables are being installed.  The lighting plan is yet to be approved by the Committee.

The toilets already being rebuilt.  The rebuilding of the toilets is being funded and undertaken by the PSHS.

Furniture and fixtures (desks, chairs, cabinets, tables, sofas) are yet to be decided on.  Equipment (air conditioning units, ceiling fans) are yet to be decided on.

The proceeds from the GSIS Insurance claim are about to be released.